Mt Cattlin Spodumene Project

Information

Client: Galaxy Lithium Aust. Ltd
Location: Great Southern, Western Australia
Scope: 40km DN250 Water Pipeline plus various facilities
Date: 2017
Project Length:
Value: $0.48M

Industry

Mining

Water

OSD’s Role

  • Feasibility Study
  • Strategic Planning

Summary

Galaxy Resources Australia Limited (Galaxy) is intending to increase production at its Mt Cattlin Spodumene Project to 1.6mtpa. The increased production rate will require a total water demand of 626,000kl pa which is some 342,000kl pa in excess of that currently available from tailings return, site catchment dams and the existing borefield.

OSD was commissioned to investigate the water demand, assess potential water resources and develop a strategy for meeting the supply shortfall. The investigation produced recommendations for mine site dam and pumping upgrades supplemented by a new tank farm and 40km supply pipeline.

Recent Projects header

Recent Projects

Outstanding Service Delivery

Work with us

OSD IS EVOLVING!

We are pleased to announce that we have changed the name of one of our key subsidiaries, OSD Pty Ltd to Verbrec Infrastructure Services Pty Ltd as of 17 October 2022.

Rebranding to Verbrec represents our evolution and continued growth by leveraging emerging technologies, thereby remaining at the forefront of an ever-changing industry. Evolution, engineered.

Verbrec has expanded its capabilities significantly to support our clients’ needs and built what we are today, a leading mid-tier engineering, infrastructure, and training company operating across the entire asset life cycle.

Important: Please note that this is a rebranding exercise and as such, will be a name change only; there is no other change to the details of the business. The entity’s beneficial ownership, ABN, registered address and all other relevant details remain the same.

Find out more about our history and plans for the future...